Pitched Roof for 67 plots Oxford House, Aylesbury

December 17, 2025 — admin
Client: MCR PropertyLocation: Oxford House, AylesburyProject Duration: 30 weeksScope of Works: Installation of interlocking Marley tiles, loft insulation, felt and battens, Velux windows, lead dormers, and two-layer felt porch roofsValue: £320,000.00 BackgroundOxford House in Aylesbury required a complete pitched roof…
1

Roof Refurbishment Prince William School, Oundle

December 16, 2025 — admin
Client: East Midlands Academy TrustLocation: Prince William School, OundleProject Duration: 8 weeksScope of Works: Full refurbishment of the Art, Design & Technology block roof, including insulation upgrade, waterproofing system installation, detailing, and encapsulation of existing metal roof areasValue: £331,000.00 BackgroundPrince…
1

Asbestos Strip & Cladding Replacement – Denbigh House, Milton Keynes

December 16, 2025 — admin
Client: PCILocation: Denbigh House, Milton KeynesProject Duration:16 weeksScope of Works: Asbestos stripping, new composite panel installation, tank house cladding replacement, multiple flat roof installationsValue: £540,000.00 BackgroundDenbigh House required urgent removal of hazardous asbestos roofing materials alongside comprehensive roof and cladding…
1

Flat & Pitched Roof Replacement Witney Campus, Oxfordshire

December 16, 2025 — admin
Client: Abingdon & Witney CollegeLocation: Witney Campus, OxfordshireProject Duration: 8 weeksScope of Works: Flat roof replacement with thermal upgrade, full pitched roofreplacement including new hand-cut roof and associated stoneworkValue: £173,000.00 BackgroundAbingdon & Witney College required essential roofing works to improve…
1

Heritage Roof Restoration Rock House, Stamford

December 15, 2025 — admin
Client: Linx ConstructionLocation: Rock House, StamfordProject Duration: 10 weeksScope of Works: Full pitched roof replacement, timber and lead renewal, heritage-compliant restorationValue: £210,000.00 BackgroundRock House is a prominent heritage property in Stamford, requiring specialist roofing works to restore and protect the…
1

Heatherbrook Primary School

November 15, 2025 — admin
Here we were tasked up grading the schools u-values and fix an ongoing leaking roof.  An overlay was carried on the larger roof section with a 3 layer Garland system achieving part L regulations and a new 25 year single…